Summary
Everest Metals Corporation’s September 2026 Quarterly Activities Report outlines substantial progress across its three core Western Australian projects. At the Mt Dimer Taipan Gold Project, mining and ROM stockpiling continued under the non-dilutive Right to Mine Agreement with MEGA Resources and Bain, with ROM material increasing to more than 142,000 tonnes by 30 September 2026, and material scheduled for third-party toll processing; the company also commenced a 2,000m EIS co-funded RC drilling program on adjacent exploration tenure, while post-quarter it reported an updated JORC 2012 Mineral Resource of 975,000t at 1.37g/t Au for about 43,000oz, including Measured and Indicated resources for the first time. At the Mt Edon Critical Mineral Project, EMC appointed Hall Chadwick as exclusive strategic adviser to assess funding, partnership and transaction pathways with an initial focus on US and allied markets, progressed an independent validation program on rubidium supply-chain and strategic funding opportunities, and continued advancing development approvals and metallurgy around its 4.3Mt at 0.23% Rb2O and 0.10% Li2O resource; post-quarter metallurgical work achieved rubidium extraction of up to 90% in batch testing. At the Revere Gold Project, EMC secured Mining Lease M51/905 to 2047 covering the Big John resource, advanced permitting and technical studies, appointed Como Engineers for a Scoping Study due in the March 2027 quarter, completed a transaction to lift its Goodins East JV interest to 56% and reduce certain royalty burdens, and post-quarter completed 7,877m of aircore drilling across Armstrong, Big John and Tree Reef. Corporate updates included the issue of 1,000,000 shares tied to Revere tenure consolidation, lodgement of the FY2026 Annual Report and governance documents, and a cash balance of about A$4.1 million at 30 September 2026.
Key Points
  • Mt Dimer mining and ROM stockpiling increased to more than 142,000 tonnes under the Right to Mine Agreement with MEGA Resources and Bain.
  • Mt Dimer material was scheduled for third-party toll processing, providing a processing pathway without building a standalone plant.
  • A 2,000m RC drilling program began on Mt Dimer exploration licence E77/2383 with up to A$145,000 co-funding under WA’s Exploration Incentive Scheme.
  • Post-quarter, Mt Dimer’s Mineral Resource was updated to 975,000 tonnes at 1.37g/t Au for approximately 43,000 ounces, including Measured and Indicated categories for the first time.
  • Hall Chadwick was appointed strategic adviser for Mt Edon to assess commercial, funding and transaction options focused on the United States and allied markets.
  • Mt Edon’s strategic review includes independent analysis of rubidium supply-chain vulnerability, demand and potential funding pathways.
  • Mt Edon holds a JORC 2012 Mineral Resource of 4.3Mt at 0.23% Rb2O and 0.10% Li2O.
  • Post-quarter Mt Edon metallurgical work achieved rubidium extraction of up to 90% in batch testing, with continuous kiln trials returning 50–60% before further optimisation.
  • Revere received Mining Lease M51/905 to 2047, securing tenure over the entire 228,307oz Big John Mineral Resource.
  • Como Engineers was appointed to complete a Revere Scoping Study in the March 2027 quarter based on the existing 260,780oz gold Mineral Resource.
  • EMC agreed to increase its Goodins East JV interest to 56% and reduce royalty obligations across parts of the Revere project.
  • A 7,877m aircore drilling program across Armstrong, Big John and Tree Reef was completed post-quarter, with assay results expected in early December 2026.
  • The company issued 1,000,000 ordinary shares in September 2026 as part consideration for Revere tenure consolidation.
  • EMC lodged its FY2026 Annual Report, Corporate Governance Statement and Appendix 4G on 18 September 2026.
  • EMC reported a cash position of approximately A$4.1 million as at 30 September 2026.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should refer to the full announcement here for further information.