Centaurus Metals Limited announced the approval of connecting its Jaguar Nickel Sulphide Project to Brazil's national high-voltage power grid, ensuring access to low-cost, reliable electricity. This strategic move secures a 20MW power allocation and involves extending a 36km transmission line to the project's main substation. The initiative is expected to lower long-term operating costs and support the project's competitive positioning in the global nickel market. All required environmental and mining permissions for the construction have been obtained, and a financial guarantee will be lodged to secure the power allocation. This development represents a significant step in advancing the project, mitigating risks, and enhancing operational efficiencies.
Key Points
Centaurus Metals has received regulatory approval to connect the Jaguar Nickel Sulphide Project to Brazil's national 230kV power grid.
The approval secures an initial allocation of 20MW of power, providing reliable and low-cost electricity.
This connection will significantly reduce operating costs and support the project's position in the bottom quartile of the global nickel cost curve.
Construction involves a 36km extension from an existing transmission line to Jaguar's main substation.
All necessary environmental and mining approvals for construction have been secured.
Centaurus has agreed to participate in load shedding until regional transmission upgrades are completed, projected by mid-2032.
A R$9.7 million (A$2.7 million) guarantee will be lodged with ONS to secure the power allocation, linked to the Final Investment Decision.
This milestone is critical for advancing the Jaguar project towards development, providing a competitive edge through reduced risks and costs.