- Cochrane Hill Ore Reserve is currently 15.4 Mt at 1.0 g/t Au for 510,000 ounces of gold.
- Key design changes will process sorted ore at the proposed 15-Mile processing facility.
- Elimination of the need for a processing plant at Cochrane Hill will reduce capital costs.
- This approach aims to significantly lower environmental and social impacts.
- Ore sorting trials resulted in a concentration of 89.7% of gold from the bulk sample.
- The redesign is expected to be completed in Q4 FY25.
- Community engagement with First Nations is prioritized during the development phase.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
Deep Yellow Limited (DYL) ORDINARY FULLY PAID |
Energy |
$1,810 |
Appendix 5B September 2024 Quarterly Cashflow
|
22 Oct 2024 8:10AM |
$1.540 |
$1.860 |
risen by
20.78%
|
|
DYL - Price-sensitive ASX Announcement
Full Release
Key Points
- Net cash outflow from operating activities was $5,695,000.
- Total cash and cash equivalents at end of the quarter amounted to $247,280,000.
- Significant exploration and evaluation costs incurred totaling $4,113,000.
- Focus on advancing mining projects indicates ongoing commitment in the sector.
- The report covers financial operations for the quarter ending 30 September 2024.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
Deep Yellow Limited (DYL) ORDINARY FULLY PAID |
Energy |
$1,810 |
September 2024 Quarterly Activities Report
|
22 Oct 2024 8:10AM |
$1.540 |
$1.860 |
risen by
20.78%
|
|
DYL - Price-sensitive ASX Announcement
Full Release
Key Points
- Tumas 1, 2 and 3 Measured Mineral Resource upgraded to 38.5 Mlb
- Total Measured and Indicated Mineral Resource now stands at 106.2 Mlb
- Project execution controls and systems largely established
- On track to make a Final Investment Decision in late Q4 2024
- Extensive hydrogeological drilling program completed
- Pilot metallurgical testwork successfully completed
- Appointment of Craig Barnes as CFO and Jim Morgan as Head of Project Delivery
- Global nuclear outlook continues to strengthen
- Cash position at end of September 2024 quarter $247.3M
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
Peregrine Gold Ltd (PGD) ORDINARY FULLY PAID |
Materials |
$28 |
Tin Can Trend Exploration Moves Into High Gear
|
22 Oct 2024 8:10AM |
$0.165 |
$0.280 |
risen by
69.70%
|
|
PGD - Price-sensitive ASX Announcement
Full Release
Key Points
- Exploration on the Tin Can gold trend is currently underway.
- 2024 drilling extended the Tin Can trend west 250m.
- Initial hole returned 4m at 9.0g/t Au.
- Soil sampling returned up to 512ppb Au.
- Aeromagnetics correlates well with gold anomalies.
- Induced Polarisation survey planned to highlight potential blind mineralisation.
- High-Level Review of Exploration Strategy is underway.
- Peregrine aims for a major >1moz gold discovery.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
Caravel Minerals Limited (CVV) ORDINARY FULLY PAID |
Materials |
$84 |
Key Water Agreement - Caravel Copper Project
|
22 Oct 2024 8:10AM |
$0.160 |
$0.150 |
fallen by
6.25%
|
|
CVV - Price-sensitive ASX Announcement
Full Release
Key Points
- Caravel Minerals has entered into an Option Agreement to acquire Dalmeny Water Pty Ltd.
- Dalmeny Water holds groundwater extraction licences sufficient for the Caravel Copper Project.
- The agreements secure access to private land for the development of the proposed borefield.
- Water for the project will be sourced from aquifers unsuitable for agricultural purposes.
- The Option Agreement has a term of three years with an extension option.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
St Barbara Limited (SBM) ORDINARY FULLY PAID |
Materials |
$423 |
Update on Touquoy Mine Renewable Energy Investigation
|
22 Oct 2024 8:10AM |
$0.455 |
$0.390 |
fallen by
14.29%
|
|
BPM Minerals Limited (BPM) ORDINARY FULLY PAID |
Materials |
$7 |
Further Assay Results Extend the Louie Gold Discovery
|
22 Oct 2024 8:10AM |
$0.120 |
$0.082 |
fallen by
31.67%
|
|
BPM - Price-sensitive ASX Announcement
Full Release
Key Points
- Final assay results from the Louie Gold Discovery drilling.
- Significant intercepts include 25m at 1.27 g/t Au.
- High-grade core defined over 600m within a 1,000m long anomaly.
- Project located near Mount Gibson Gold Project, enhancing its potential.
- BPM is fully funded for further exploration.
- Plans for a 2,500m RC drilling program at Louie.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
Elders Limited (ELD) ORDINARY FULLY PAID |
Consumer Staple |
$1,469 |
Change in substantial holding
|
22 Oct 2024 8:09AM |
$8.600 |
$7.680 |
fallen by
10.70%
|
|
Finder Energy Holdings Limited (FDR) ORDINARY FULLY PAID |
Energy |
$69 |
Notice of 2024 Annual General Meeting/Proxy Form
|
22 Oct 2024 8:09AM |
$0.049 |
$0.180 |
risen by
267.35%
|
|
Sheffield Resources Limited (SFX) ORDINARY FULLY PAID |
Materials |
$61 |
Quarterly Activities/Appendix 5B Cash Flow Report
|
22 Oct 2024 8:09AM |
$0.290 |
$0.155 |
fallen by
46.55%
|
|
SFX - Price-sensitive ASX Announcement
Full Release
Key Points
- Sheffield Resources Limited reported cash reserves of approximately $9 million.
- The South Atlantic Project in Brazil is progressing, with an option to acquire 20% interest.
- Thunderbird Mineral Sands Mine continues to perform strongly with stable production metrics.
- Ongoing improvements in mining processes are being implemented.
- An investor and shareholder webinar is scheduled for 24 October 2024.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
Proteomics International Laboratories Ltd (PIQ) ORDINARY FULLY PAID |
Health Care |
$50 |
September 2024 Quarterly Activities Report and Appendix 4C
|
22 Oct 2024 8:09AM |
$0.780 |
$0.308 |
fallen by
60.58%
|
|
PIQ - Price-sensitive ASX Announcement
Full Release
Key Points
- World first blood test for esophageal cancer shows 94% accuracy.
- PromarkerD demonstrates high accuracy in predicting chronic kidney disease for type 1 diabetes.
- Targeting US and Australian launches of PromarkerD in 2025.
- PromarkerEndo and PromarkerEso tests are advancing.
- ISO 17025 certification successfully renewed.
- Appointment of Dr. James Williams as independent non-executive director.
- Cash reserves reported at $5.10 million with a forecast R&D tax incentive rebate of $2 million.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
Lotus Resources Limited (LOT) ORDINARY FULLY PAID |
Energy |
$489 |
Quarterly Activities and Cash Flow Reports - September 2024
|
22 Oct 2024 8:09AM |
$0.315 |
$0.180 |
fallen by
42.86%
|
|
LOT - Price-sensitive ASX Announcement
Full Release
Key Points
- Completion of Kayelekera FEED program allows for accelerated restart.
- Time to first uranium production reduced to 8-10 months.
- Initial restart capital expenditure reduced to US$50 million.
- Two conditional uranium offtake agreements secured for 1.5 million lbs.
- Mine Development Agreement signed with the Government of Malawi.
- Letlhakane Scoping Study confirmed long-life, high-value project.
- Drill program completed at Letlhakane, updated Mineral Resource Estimate due in November.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
APA Group (APA) FULLY PAID UNITS STAPLED SECURITIES |
Utilities |
$11,784 |
Becoming a substantial holder
|
22 Oct 2024 8:09AM |
$7.170 |
$8.960 |
risen by
24.97%
|
|
Krakatoa Resources Limited (KTA) ORDINARY FULLY PAID |
Materials |
$9 |
Successful EIS Funding For Stone Tank Nb-REE Prospect
|
22 Oct 2024 8:08AM |
$0.010 |
$0.012 |
risen by
20%
|
|
Siren Gold Limited (SNG) ORDINARY FULLY PAID |
Materials |
$20 |
IL Survey Extends Auld Creek Mineralisation to over 1.5kms
|
22 Oct 2024 8:08AM |
$0.110 |
$0.074 |
fallen by
32.73%
|
|
SNG - Price-sensitive ASX Announcement
Full Release
Key Points
- An Ionic Leach (IL) soil sampling program at Auld Creek shows that the gold and antimony mineralisation extends for at least 1.5kms and is open to the north and south.
- The IL anomalies coincide with two parallel conductive anomalies 100m apart that extend for 1.5kms and are also open to the north and south.
- IL and conventional soil geochemistry indicate that the mineralisation at the now closed Globe Progress mine continues at least 2.5kms further north through Auld Creek.
- To date, only 400m of this strike has been drill tested and contains a mineral resource (MRE) of 210koz @ 7.7g/t AuEq.
- The MRE has significant potential to contain a million-ounce gold equivalent resource.
- Siren Managing Director Victor Rajasooriar commented on the potential for growth at Auld Creek.
- The Auld Creek prospect could enhance the Mineral Resource on the Reefton Project, which currently stands at 588koz @ 4.72g/t AuEq.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
Regis Resources Limited (RRL) ORDINARY FULLY PAID |
Materials |
$4,392 |
Morgans Sales Desk Briefing
|
22 Oct 2024 8:08AM |
$2.750 |
$5.800 |
risen by
110.91%
|
|
Augustus Minerals Limited (AUG) ORDINARY FULLY PAID |
Materials |
$7 |
Justinian Extended to 3km with 16% Copper and 5.3g/t Gold
|
22 Oct 2024 8:08AM |
$0.048 |
$0.044 |
fallen by
8.33%
|
|
AUG - Price-sensitive ASX Announcement
Full Release
Key Points
- High grade rock chips assaying up to 16% copper and 5.32g/t gold identified.
- Justinian prospect extended to cover a 3.2km x 1.1km area.
- Soil sampling results indicate significant copper and gold anomalies.
- Results correlate with splaying of the Ti-Tree Shear near the Crawford Granite.
- Further mapping and sampling are planned to define mineralised structures.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
DevEx Resources Limited (DEV) ORDINARY FULLY PAID |
Materials |
$39 |
Investor Presentation - October 2024
|
22 Oct 2024 8:08AM |
$0.140 |
$0.089 |
fallen by
36.43%
|
|
CuFe Ltd (CUF) ORDINARY FULLY PAID |
Materials |
$16 |
West Arunta Land Access Agreement Executed
|
22 Oct 2024 8:07AM |
$0.009 |
$0.012 |
risen by
33.33%
|
|
Austal Limited (ASB) ORDINARY FULLY PAID |
Industrials |
$3,416 |
Change of Director's Interest Notice
|
22 Oct 2024 8:07AM |
$3.150 |
$8.110 |
risen by
157.46%
|
|
Austal Limited (ASB) ORDINARY FULLY PAID |
Industrials |
$3,416 |
Change of Director's Interest Notice
|
22 Oct 2024 8:07AM |
$3.150 |
$8.110 |
risen by
157.46%
|
|
Good Drinks Australia Ltd (GDA) ORDINARY FULLY PAID |
Consumer Staple |
- |
Q1 FY25 Results Update
|
22 Oct 2024 8:07AM |
$0.275 |
$0.320 |
risen by
16.36%
|
|
GDA - Price-sensitive ASX Announcement
Full Release
Key Points
- Q1 FY25 total volume growth of 9% vs Prior Year Comparative Period.
- Own brands grew by 12%, outperforming the overall beer market decline of 4%.
- GDA is the fastest growing manufacturer in the Australian beer market.
- Strong performance in the hospitality sector with Gage Roads Fremantle achieving 3% revenue growth.
- Investment of $500,000 planned for venue refreshment and upgrades.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
Talisman Mining Limited (TLM) ORDINARY FULLY PAID |
Materials |
$28 |
Corporate Update - Wonmunna Iron Ore Royalty
|
22 Oct 2024 8:07AM |
$0.255 |
$0.150 |
fallen by
41.18%
|
|
TLM - Price-sensitive ASX Announcement
Full Release
Key Points
- Talisman Mining Limited provides update on Wonmunna Iron Ore royalty.
- Royalty stream is 1% uncapped from Wonmunna Iron Ore Project.
- Wonmunna Project is transitioning production to Lamb Creek deposit.
- Royalty receipts total $25.6 million, including $8.6 million in FY24.
- Talisman has $5.8 million cash, no debt, and a strong shareholder base.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
Catalina Resources Ltd (CTN) ORDINARY FULLY PAID |
Materials |
$10 |
Quarterly Activities/Appendix 5B Cash Flow Report
|
22 Oct 2024 8:07AM |
$0.003 |
$0.004 |
risen by
33.33%
|
|
CTN - Price-sensitive ASX Announcement
Full Release
Key Points
- Aircore drilling program completed at Laverton Project.
- 27 holes and 1,801 meters drilled, targeting gold and REE.
- Diamond drilling planned for November 2024 at Lachlan Fold Belt Project.
- Total exploration expenditure for the quarter was A$76,000.
- Cash balance at quarter end was A$2,648,000.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
Vault Minerals Limited (VAU) ORDINARY FULLY PAID |
Materials |
$4,490 |
Resource and Reserve Statement
|
22 Oct 2024 8:06AM |
$0.390 |
$0.660 |
risen by
69.23%
|
|
VAU - Price-sensitive ASX Announcement
Full Release
Key Points
- Ore Reserve of 506,000 ounces for the Sugar Zone project.
- Mineral Resource estimate of 1.5 million ounces as of 30 June 2023.
- 93,000-meter drill program initiated for FY24.
- Significant drilling activity completed with results expected by December 2023.
- Report prepared following ASX Listing Rules and JORC Code guidelines.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.