| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Milling Started at Three Mile Hill. Target 40,000 Tonnes.
|
21 Nov 2024 8:18AM |
$0.270 |
$0.230 |
fallen by
14.81%
|
|
AWJ - Price-sensitive ASX Announcement
Full Release
Key Points
- Milling commenced on 20 November 2024 at Three Mile Hill Plant, Coolgardie.
- Around 25,000 tonnes on Three Mile Hill ROM Pad at the commencement of processing.
- Targeting minimum 40,000 tonnes parcel.
- First gold pour within seven days.
- Cash distribution to Auric expected in December 2024.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Encouraging RC Drill Results at Spargoville Project
|
15 Nov 2024 8:22AM |
$0.260 |
$0.230 |
fallen by
11.54%
|
|
AWJ - Price-sensitive ASX Announcement
Full Release
Key Points
- 17 hole RC program completed at Fugitive and Anomaly 37 Prospects.
- Fugitive Prospect results include: 7m @ 4.88g/t Au, including 3m @ 10.36g/t Au.
- Mineralised zone at Fugitive remains highly prospective for further drilling.
- First pass RC drilling at Anomaly 37 opens up new exploration targets.
- Management expresses optimism over the potential for large mineralisation.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Quarterly Activities Report
|
31 Oct 2024 1:20PM |
$0.370 |
$0.230 |
fallen by
37.84%
|
|
AWJ - Price-sensitive ASX Announcement
Full Release
Key Points
- Completion of the second processing campaign at Jeffreys Find with 6,295 ounces of gold produced.
- Generated approximately $23.48 million in revenue from the processing campaign.
- Auric secured exclusive nickel and lithium rights at the Munda Gold Project for the next eight years.
- Encouraging aircore drilling results at the Spargoville Project, particularly at Fugitive and Anomaly 37.
- The company reported a strong financial position with $4.3 million in cash at the end of the quarter.
- Acquisition of new office premises to support operational expansion.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Appendix 5B Cash Flow Report
|
31 Oct 2024 1:15PM |
$0.370 |
$0.230 |
fallen by
37.84%
|
|
AWJ - Price-sensitive ASX Announcement
Full Release
Key Points
- Cash inflow from operating activities was $3,487,000.
- Receipts from gold sales totaled $2,000,000.
- Net cash used in investing activities amounted to $685,000.
- Cash balance at the end of the quarter was $4,316,000.
- The report includes details of payments to related parties.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
WIN: Rescission of divestment of Lithium Rights at Munda
|
29 Oct 2024 6:21PM |
$0.385 |
$0.230 |
fallen by
40.26%
|
|
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Rescission of Purchase of Lithium Rights at Munda
|
29 Oct 2024 6:06PM |
$0.385 |
$0.230 |
fallen by
40.26%
|
|
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Additional Milling to Start in 10 Days of Jeffreys Find Ore
|
28 Oct 2024 8:20AM |
$0.375 |
$0.230 |
fallen by
38.67%
|
|
AWJ - Price-sensitive ASX Announcement
Full Release
Key Points
- BML Ventures executed a toll milling agreement with Focus Minerals Ltd.
- Processing of additional ore from Jeffreys Find at Three Mile Hill Plant to start on 7 November 2024.
- Initial parcel of 40,000 tonnes is set for processing, with haulage already commenced.
- Agreement includes a minimum of 50,000 tonnes to a maximum of 120,000 tonnes.
- This contract will expedite cash flow for Auric Mining.
- Completion of mining at the Jeffreys Find Project is anticipated in early 2025.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Cleansing Statement
|
24 Oct 2024 3:18PM |
$0.383 |
$0.230 |
fallen by
39.87%
|
|
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Application for quotation of securities - AWJ
|
24 Oct 2024 1:32PM |
$0.385 |
$0.230 |
fallen by
40.26%
|
|
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Proposed issue of securities - AWJ
|
23 Oct 2024 8:17AM |
$0.395 |
$0.230 |
fallen by
41.77%
|
|
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Total Gold Sales of $23.5M from Jeffreys Find Campaign
|
2 Oct 2024 8:16AM |
$0.355 |
$0.230 |
fallen by
35.21%
|
|
AWJ - Price-sensitive ASX Announcement
Full Release
Key Points
- Second toll milling campaign for 2024 completed.
- 6,295 ounces of gold produced.
- Gold sales total $23.5 Million.
- Highest sale price at AUD$3,859 per ounce.
- Average sale price at AUD$3,731 per ounce.
- Auric received an initial surplus cash distribution of $2.0 Million.
- Total production for the year has passed 7,500 ounces.
- Another toll milling campaign scheduled for end of November.
- Reconciled yield of 1.65 g/t and recovery of 93.2%.
- Greenfields contracted to mill 300,000 tonnes in 2024/2025.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Melbourne Mining Club Presentation
|
17 Sep 2024 4:32PM |
$0.325 |
$0.230 |
fallen by
29.23%
|
|
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
2024 Half Year Financial Report
|
9 Sep 2024 2:17PM |
$0.275 |
$0.230 |
fallen by
16.36%
|
|
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Spargoville Project Aircore Drilling Results
|
6 Sep 2024 8:20AM |
$0.270 |
$0.230 |
fallen by
14.81%
|
|
AWJ - Price-sensitive ASX Announcement
Full Release
Key Points
- Spargoville aircore drilling program completed with 71 holes drilled for 2,259 meters
- Fugitive and Anomaly 37 Prospects confirmed as first order targets for RC drilling
- Significant aircore results include: 4m @ 2,794ppb Au, 22m @ 246ppb Au, 11m @ 303ppb Au
- Drilling focused on gold anomalies defined by soil-auger sampling in tenements E15/1688 and E15/1689
- Follow-up includes geological interpretation and RC drilling to test gold mineralization zones
- Auric Mining Limited operates four projects in the Widgiemooltha-Norseman area
- The latest results reaffirm the potential within the E15/1688 tenement
- Heritage survey completed allowing for RC drilling at both Fugitive and Anomaly 37 Prospects
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Gold Sales for 2024 Exceed A$18M. Toll Milling Continues.
|
29 Aug 2024 8:05AM |
$0.295 |
$0.230 |
fallen by
22.03%
|
|
AWJ - Price-sensitive ASX Announcement
Full Release
Key Points
- Gold sales for 2024 exceed A$18.23 million
- Highest gold price achieved is A$3,727 per ounce
- 154,000 tonnes delivered to the mill
- Current campaign to conclude on 4 September 2024
- First cash of A$3.0 million to be received by Auric shortly
- Jeffreys Find Gold Mine expected to generate over A$25 million in gross gold sales for 2024
- Further campaign planned at Greenfields Mill towards the end of the year
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Change of Director's Interest Notice - Steven Morris
|
28 Aug 2024 11:56AM |
$0.295 |
$0.230 |
fallen by
22.03%
|
|
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
WIN: Munda Agreement with Auric Mining Ltd concluded
|
27 Aug 2024 8:05AM |
$0.300 |
$0.230 |
fallen by
23.33%
|
|
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Settlement and Completion with WIN Metals Ltd re Munda
|
27 Aug 2024 8:05AM |
$0.300 |
$0.230 |
fallen by
23.33%
|
|
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Gold Sales in August Total $6.3M. Toll Milling Continues
|
16 Aug 2024 8:22AM |
$0.240 |
$0.230 |
fallen by
4.17%
|
|
AWJ - Price-sensitive ASX Announcement
Full Release
Key Points
- Second gold milling campaign for 2024 produced further cash with gold selling at an average of A$3,697 per ounce.
- The Greenfields Mill is contracted to process 150,000 tonnes of ore for the current campaign.
- Nearly 129,000 tonnes have been delivered to the Mill as of 14 August 2024.
- Total gross gold revenue for the campaign is A$10.8 million, with A$6.3 million generated in August.
- Auric will receive A$3.0 million from BML within a month, including A$2.0 million surplus cash distribution and A$1.0 million repayment of working capital.
- The Joint Venture between Auric and BML operates the Jeffreys Find Gold Project with a 50:50 profit split after direct costs.
- Auric projects to extract over 20,000 ounces of gold in 2024.
- Further gold milling campaigns are scheduled for November/December 2024.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
NWR Perth Presentation
|
30 Jul 2024 1:31PM |
$0.225 |
$0.230 |
risen by
2.22%
|
|
AWJ - Price-sensitive ASX Announcement
Full Release
Key Points
- Auric’s tenements located in the Goldfields of Western Australia.
- Jeffreys Find Gold Mine acquired from Mincor Resources in September 2020.
- Stage One mining at Jeffreys Find completed in November 2023 with 9,741 ounces of gold produced.
- Contract to process a minimum of 300,000 tonnes of ore in 2024.
- Munda Gold Project holds approximately 200,000 ounces of gold resources.
- Grade control drilling at Munda completed in January 2024.
- Plan to commence open pit trial mining at Munda in Q1 2025.
- Auric to remain gold-focused with exploration at Spargoville and Higginsville.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Quarterly Activities Report
|
26 Jul 2024 8:21AM |
$0.225 |
$0.230 |
risen by
2.22%
|
|
AWJ - Price-sensitive ASX Announcement
Full Release
Key Points
- Auric Mining Limited completed its first gold processing campaign at Jeffreys Find Gold Mine, generating $4.46 million in revenue.
- Stage 2 mining at Jeffreys Find aims to extract a minimum of 300,000 tonnes of ore in 2024/2025 with round-the-clock operations.
- Grade control drilling and mine planning are significantly progressed at the Munda Gold Project, with several high-grade intercepts noted.
- Auric is undertaking further RC drilling at Spargoville, showing significant basement gold targets.
- The company reported a strong financial position with $3.4 million in cash at the end of the quarter.
- Auric held its Annual General Meeting on the 24th of May 2024, with all resolutions passed.
- The company has lodged three new tenement applications and acquired one new tenement during the quarter.
- No farm-in or farm-out agreements are currently in place for Auric.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Quarterly Appendix 5B Cash Flow Report
|
26 Jul 2024 8:21AM |
$0.225 |
$0.230 |
risen by
2.22%
|
|
AWJ - Price-sensitive ASX Announcement
Full Release
Key Points
- Net cash outflow from operating activities: $600,000
- Net cash inflow from financing activities: $2.528 million
- Total cash balance at the end of the period: $3.487 million
- Gold sales from Jeffreys Find: $4.766 million YTD
- Expenditures on exploration and evaluation: $451,000
- Administration and corporate costs: $193,000
- Payments to related parties: $159,000
- No proceeds from borrowings
- No dividends paid
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
Milling of 150,000t Underway. Cash to Auric within Weeks
|
25 Jul 2024 8:23AM |
$0.220 |
$0.230 |
risen by
4.55%
|
|
AWJ - Price-sensitive ASX Announcement
Full Release
Key Points
- Commencement of second gold milling campaign for 2024.
- 150,000 dry metric tonnes to be processed from Jeffreys Find Gold Mine.
- Toll milling started at Greenfields Mill with 75,600 tonnes of ore delivered.
- Milling expected to conclude in early September 2024.
- Additional gold milling campaigns scheduled later in 2024.
- First surplus cash distribution to Auric expected in late August.
- Auric and BML to benefit from the high gold price of $3,600 an ounce.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
WIN: Munda Agreement with AWJ yields $1.2m (Updated)
|
23 Jul 2024 5:32PM |
$0.230 |
$0.230 |
fallen by
0%
|
|
| Auric Mining Limited (AWJ) ORDINARY FULLY PAID |
Materials |
$43 |
WIN: Munda Agree. with Auric Mining Ltd yields $1.2m for WIN
|
23 Jul 2024 9:05AM |
$0.225 |
$0.230 |
risen by
2.22%
|
|
AWJ - Price-sensitive ASX Announcement
Full Release
Key Points
- Divestment of Nickel and Lithium rights to 150m below surface over a portion of M15/87 to Auric Mining Ltd.
- Transfer of non-core tenure including multiple prospecting and exploration licenses.
- The transaction provides WIN with access to in-pit water for mining operations.
- The deal nets a minimum of $1.2 million to WIN over the next 12 months.
- Consideration payable by Auric to WIN includes a $100,000 deposit, $600,000 at settlement, $300,000 on 1 December 2024, and $200,000 on 1 June 2025.
- Ongoing access fees for water usage will also be paid by Auric.
- The nickel resource at Munda is mainly below the level divested and fits within WIN’s long-term strategic plans.
- Auric gains the ability to commence a trial pit for gold mining at the Munda Gold Project in Q1 2025.
- Auric will also acquire access to stored water from WIN, easing operational water constraints.
- Both companies view the agreement as a mutually beneficial arrangement, allowing focused development of respective projects.
IMPORTANT NOTE: This information is autogenerated and has not been reviewed for accuracy or completeness. You should
refer to the full announcement here for further information.