Italy's solar boom

The massive increase in Italy's solar power capacity over the past 12 months puts the spotlight on the country's renewables policy - and illustrates just how quickly big solar can be installed.
By · 27 Jan 2011
By ·
27 Jan 2011
comments Comments

opportunity:energy

Just a few days ago I was all set to start an article on the fast-rising pace of the Italian solar market, based on the available data from GSE (the Italian Government's Energy Agency). I was going to comment on what I thought would be a banner year, with total installations for almost 3,000 MW, over four times the previous year's levels (718 MW in 2009), with a total installed capacity now approaching 4,000 MW. My figures were wrong.

The Gestore Servizi Energetici (GSE) has now issued an updated press release with their latest forecasts on photovoltaic power installed capacity in Italy at the end of 2010. It is now anticipated that cumulative installed capacity should be around 3,000 MW with over 150,000 plants producing electricity throughout the country. This would mean an increase of 1.850 MW for 2010, or 160 per cent more than 2009.

There is a catch though: given the skyrocketing demand for grid connection of new PV plants, the Italian government decided last year to warrant 2010-level incentives to all PV plants built within 2010, but not yet connected (such is the backlog of requests to the national grid), with a connection deadline of 30 June 2011. Well, on this side, GSE received requests for additional 55,000 PV plants, totalling an astonishing further 4,000 MW. This means that total capacity at end of 2010 is around 7,000 MW, up from just 1142 MW 12 months before.

These are striking results, highlighting two important facts: 1) Solar PV power, if anyone hadn't noticed before, is the quickest source of energy to install at industrial scale, given its simple design, modularity and scalability; 2) The incentive schemes have to be carefully planned and frequently reviewed based on global market dynamics, and it's clear, now, that feed-in tariffs can and should be reviewed downwards much quicker than previously envisaged. Solar power is becoming cheaper and cheaper, outpacing any conservative prediction.

What's the latest update, then, for the global PV market? The world's five main markets in 2010 were Germany, Italy, Czech Republic, USA and Japan. Germany took the lead with over 6.5 GW installed in 2010; Italy is now closing in at 6 GW; 'shooting star' Czech Republic has 1.5 GW; US and Japan sit at around 1 GW each (all figures are rough estimates to be confirmed).

China and other Asian countries are entering the market now and will soon prove more important in the global arena. The once mighty Spanish market is now dead after a terrible mismanagement of the incentives scheme, which led first to capping and then to retroactive measures that have undermined Spain's credibility in all investment sectors.

Is this something we should be worried about for Italy, Germany and in general for all renewable energy markets? If there is a lesson to be learnt, it is that what Spain (or Czech Republic) did must not be replicated. Capping the market leads to uncertain dynamics as it risks stalling the industry for many months a year. But even worse is putting in place retroactive measures, which inevitably lead to mistrust in all investment sectors for the affected country (we already know we can't rely on banks, but what if we can't trust the government either?).

What lies ahead

There is one obvious way forward: By trimming down incentives as needed. Feed-in tariffs are meant to stimulate a promising market in its infancy until it becomes self-sustaining. Germany has always moved in this direction and recently planned substantial reductions for mid-2011.

We can imagine similar moves might be put in place soon by Italy's GSE, even though the new Conto Energia (the scheme's name) is now fully set and operative since January 1. The PV industry might decide to negotiate with Italian authorities in order to change tariffs starting next year or before, so as to maintain investments stability in the short term while readying a revised plan for years to come. If no steps are taken, the current market conditions will, in my opinion, lead to something like 10,000 MW installed this year alone, and more next year.

One thing is certain, the solar industry is making its mark on the Italian energy market, triggering investment, job creation and tax revenue (which substantially reduces the actual burden of incentives on the government's finances). It has grown to such levels that solar panel production plants are being built and planned by the likes of ENEL and Sharp. This is real business that cannot be dismissed.

On top of this, the renewable energy industry is quickly helping to displace the need for fossil fuels. Italy's been named many times, lately, as being at risk of not achieving its EU 2020 commitments. Chances are, the path taken is a much more virtuous one than what was conservatively stated before. The 8 GW 2020 target for solar power will be reached by this Spring in Italy, 10 years ahead of time. A new target will now have to be devised (30-50 GWs?).

Going beyond financial thinking, we can now also assess the impact of solar energy to Italy's electricity production. 7 GW of PV power will yield well over 8 GWh of electricity per year, almost 2.5 per cent of the nation's electricity consumption, while still covering a microscopic share of the country's land (most of which being roofs).

Three years ago Italy's solar installations had virtually zero impact, with 42 GWh produced in 2007. Moreover, it is worth noting that the 6 GW installed in 2010 alone will produce about the same amount of electricity as a 1 GW nuclear power plant: It took 12 months for planning approval, construction and grid connection of thousands of distributed systems.

Nuclear plants are a different matter: the complex design, the H&S and environmental concerns, and a very slow construction pace mean that such power plants take 7-10 years or more from the moment a decision is taken to the moment the power switch is turned on. It is something we cannot plan on, as Italy itself is finding out, while reviewing plans for future nuclear installations (in 2025 maybe?). On top of this, the price tag for a nuclear plant is most uncertain.

Food for thought.

Carlo Ombello writes about sustainability and renewable energy technology. This article first appeared on his blog opportunity:energy, and was reproduced with permission.

Google News
Follow us on Google News
Go to Google News, then click "Follow" button to add us.
Share this article and show your support
Free Membership
Free Membership
Carlo Ombello
Carlo Ombello
Keep on reading more articles from Carlo Ombello. See more articles
Join the conversation
Join the conversation...
There are comments posted so far. Join the conversation, please login or Sign up.